Planning direct-bonded linings around electrical first fix
Agree the finished wall position before the electrician fixes the details that depend on it.

Electrical first fix and bonded wall linings need a shared setting-out plan. The electrician needs the proposed finished face, while the drylining installer needs the accepted routes and box positions. Settle those details before either trade works from an assumed wall thickness. The shared plan gives both trades a coordinated starting point and a clear handover.
Use a finished face that has been measured
Survey the background before choosing the lining position. Existing masonry can lean, step or carry remnants of old finishes. Mark the intended face from the actual high points and the selected lining system, then check how that position meets door frames, windows and adjoining walls. Record the reference in a form both trades can use.
An electrical drawing based on the bare masonry face can leave boxes and fittings in the wrong relationship to the new surface. Equally, a lining moved further into the room after first fix can invalidate earlier setting-out. Give changes to the finished face a revision reference and communicate them to the electrician before the affected work continues. A few millimetres scribbled on an unrelated sketch is easy to miss.
Agree the background before routing work begins
Decide which existing finishes will stay and which need removal. British Gypsum's DriLyner Dab system has defined background and board requirements. Its White Book asks for services and heavy fixtures to be planned early. Use the chosen system's actual detail when coordinating the wall; the common label dot and dab does not describe every installation condition.
If the wall needs repair or investigation, identify that work before first fix is treated as ready. Opening a wall later to deal with an unresolved defect can disturb newly installed services. The person managing the sequence should identify which elevations are released, which are excluded and who accepts them. Keep that decision separate from the electrician's checks on the electrical installation.
Mark boxes against the room, not just the wall
Draw outlets and switches in relation to doors, worktops, furniture and equipment. Ask the occupier to confirm the items that have fixed positions. A socket may be accurately placed on the wall yet become inaccessible behind a cabinet. Where the furniture layout is provisional, label it and decide which electrical decisions can sensibly be fixed now.
Agree how the selected boxes and fittings relate to the lining build-up and how they are supported. Give product information to the relevant designers rather than asking the drylining installer to improvise around whatever arrives. HSE's electrical guidance identifies competence as necessary for the work being undertaken. Electrical selection, routing, isolation and testing should remain with appropriately competent people, with the lining team coordinating its own construction.

Scroll sideways to see the full table. Keyboard: focus the table, then use the arrow keys.
| Item | Shared reference | Decision to settle |
|---|---|---|
| Finished wall face | Marked setting-out line and section | Agreed position before boxes are fixed |
| Socket or switch | Elevation and fitting reference | Location, support and relationship to the lining |
| Cable route | Electrical design information | Compatibility with the selected wall construction |
| Wall-mounted equipment | Equipment and fixing schedule | Support independent of decorative appearance |
| Lining handover | Accepted elevation list | Work complete and safe for the next trade |
Check the route rather than assuming the cavity is free
A bonded lining has an intended attachment arrangement. Its space should not be treated as an unrestricted channel for services. Ask the electrician and lining designer to coordinate routes with the selected system, including treatment around openings and at the perimeter. The agreed electrical design must account for the installation conditions rather than assuming that concealment behind board resolves them.
Where a route conflicts with the lining, compare the appropriate alternatives before boarding. That might mean a revised service route or a different lining construction, subject to design. Keep the reason for the decision with the drawing. It helps prevent a later return to the rejected route when a different installer takes over.
Large service requirements deserve their own discussion. A framed or independent lining has a different support and space arrangement from a bonded lining. It may be considered where appropriate, but it still needs its own specification. Changing the construction affects reveals, trims and room dimensions, so review those details alongside the services.
Include the wall-mounted loads in first-fix information
A display screen, radiator or cabinet can require a fixing arrangement that reaches beyond the board face. Give the designers the actual item, position and load information. State which trade provides any support or preparation needed before lining and who later installs the fitting. The electrical point beside an item and the means of supporting that item are separate parts of the coordination.
For a commercial unit awaiting a tenant, distinguish known equipment from unspecified future fit-out. Record what the current construction provides without claiming that arbitrary later fittings can be attached anywhere. The incoming tenant needs the wall type and relevant fixing information so their project team can design later work. Leave any assumptions about future loads clearly identified.
Set a handover point before boards conceal the work
Agree what must be complete before the lining installer starts each elevation. The record should identify the released area, current drawing revision and any outstanding items. The electrician should confirm the relevant electrical readiness and safety arrangements; the drylining installer should confirm that the accepted wall can be lined as specified. Neither trade should be expected to certify the other's work merely by starting its own.
Photographs can help record the routes before concealment when tied to clear wall and room references. Keep them with the project documents, observing any building-security restrictions. They supplement the electrical and construction records rather than replacing later checks before drilling or alteration. A photograph may omit depth, a concealed return or a subsequent change.
If one part is incomplete, mark its boundary and agree whether work elsewhere can proceed. A precise exception is easier to manage than declaring an entire room ready while relying on everyone to remember an unfinished box. Record how that exception will be closed and who needs access for the return visit.

Protect the coordinated positions through finishing
Board openings should follow the accepted positions and suitable system details. Where a fitting appears misplaced, resolve the cause before enlarging the opening or filling around it. A surface patch can hide a setting-out error without correcting support or the relationship between the box and finished face. Ask the responsible trades to agree the repair boundary.
After jointing, identify who returns to fit accessories and who deals with any resulting surface damage. Include the decoration boundary so that a small correction does not leave an unexplained unpainted patch. Inspect the finished arrangement with the relevant equipment and furniture positions in mind. The room needs usable fittings as well as tidy board joints.
Put the unresolved decisions into the enquiry
For a Nottinghamshire lining project, bring the wall photographs, proposed lining section and electrical layout to the discussion. Explain whether first fix is complete, partially complete or still being designed. Include the surfaces that will remain and any planned equipment. Call 01623 579297 to discuss the drylining work and agree how to provide those records.
Ask the quotation to identify accepted preparation, lining products, openings and making good. List electrical work separately and confirm the interface with the appointed electrician. If the finished wall position is still unknown, settle the survey or design needed to establish it before treating box positions as final. That sequence gives both trades a stable reference and makes later changes easier to identify.
Questions and answers
Should sockets be set out before the new wall face is agreed?
Agree their required positions with the electrical designer, but coordinate the actual installation with the accepted finished face and lining construction. Update both trades if that face changes.
Does the drylining quotation include electrical work?
Only where the agreed scope expressly says so. Identify the appointed electrical trade and the handover between packages, including openings, support, testing responsibilities and surface reinstatement.
Sources and further reading
- British Gypsum White Book DriLyner DabRelease/version: 6 August 2024Source checked: 21 November 2026
- British Gypsum DriLyner DabRelease/version: 7 November 2025Source checked: 21 November 2026
- HSE electricity frequently asked questionsContains public sector information licensed under the Open Government Licence v3.0. Source: Health and Safety Executive.Release/version: Current official page; individual FAQ undatedSource checked: 21 November 2026